Mud Dredging in Ria Rio Reservoir Has Reached 40 Percent

It is also carried out to minimize flooding on Jalan Perintis Kemerdekaan and residential areas in Kayu Putih

The mud dredging process in the Ria Rio Reservoir that has been ongoing since last February has reached 40 percent.

Every day, seven heavy equipments are deployed to dredge the reservoir, which covers about eight hectares with approximately six meters depth.

Pulo Mas Jaya to Revitalize Ria Rio Reservoir

East Jakarta Water Resources (SDA) Sub-agency's Maintenance Division Head Puryanto said that dredging was done to accommodate water in large quantities when rain pours.

"It is also carried out to minimize flooding on Jalan Perintis Kemerdekaan and residential areas in Kayu Putih," he said, Wednesday (6/10).

He added it was actually targeted to be completed within four months but impossible due to COVID-19.

"So we target it at least by the end of this year," he closed.

Linked News
Popular News indeks
  1. 21 Parking Spots to Make Your Jakarta 499th Anniversary Experience Seamless

    access_time26-06-2026 remove_red_eye861 personAldi Geri Lumban Tobing
  2. Over 11 Kilometers of Overhead Utility Cables Removed in West Jakarta

    access_time26-06-2026 remove_red_eye709 personBudhi Firmansyah Surapati
  3. Celebrating Jakarta`s 499th Anniversary at HI, Please Use Public Transportation

    access_time26-06-2026 remove_red_eye703 personAldi Geri Lumban Tobing
  4. JIS-Ancol Integrated Infrastructure Officially Activated

    access_time23-06-2026 remove_red_eye644 personDessy Suciati
  5. Jakarta Steps Up to the Plate as PON 2028’s Support System

    access_time24-06-2026 remove_red_eye585 personFakhrizal Fakhri